Baseview Custom Home: Start of Framing

See this content in the original post

The first floor joist system being installed. Todd and crew are working on the stairway opening to the crawl space.

Steel Pipe columns ready for install!

See this content in the original post

The floor is decked and the wall layout is starting.

Detail of wall squash blocking at foundation wall.

See this content in the original post

View from the dining room into the kitchen....a nice wide open space!

The first wall is up!  We are using 2x6 exterior walls due to the 10' ceilings.